Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.250 | 0.75 | 0.750 | 0.000 |
68W186 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6008 (1) /III (2) / 21-37 (MLA) 2017 TCII
TS Amount (lakhs) : 109.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
109.76
Resanction Cost :
109.76
Tentative Cost :
109.76
Exp. Upto Last Fy : 93.06
For CFY 2024-2025
Remaining : 16.70
Demand : 16.70
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 93.06
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 90 %
Sanction on :
2 years 7 months ago
11 Dec 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.90 किमी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण कर लिया गया है अवशेष पहाड़ कटान का कार्य प्रगति पर है। -- as on 25-Jun-2024
Physical Peramenters