Work Profile Report [68W186]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6008 (1) /III (2) / 21-37 (MLA) 2017 TCII
TS Amount (lakhs) : 109.76 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
109.76
Resanction Cost :
109.76
Tentative Cost :
109.76
Exp. Upto Last Fy :
93.06
For CFY 2024-2025
Remaining :
16.70
Demand :
16.70
Allotment :
1.94
Exp in CFY :
1.94
Total Up to Date Exp :
95.00
Work completed
Sanction on : 3 years 1 week ago
11 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
भौतिक कार्य पूर्ण। -- as on 28-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: