Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 0.300 | 0.85 | 0.000 | 0.000 |
68W204 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. of Uttarakhand E- letter No. 25463 PWD Anubhag-2, Dehradun 03-08-2022
TS Amount (lakhs) : 21.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.51
Resanction Cost :
31.51
Tentative Cost :
31.51
Exp. Upto Last Fy : 21.33
For CFY 2024-2025
Remaining : 10.18
Demand : 10.18
Allotment : 4.96
Exp in CFY : 4.96
Total Up to Date Exp : 26.29
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
1 year 11 months ago
03 Aug 2022
Tentative Completion date:
2 days 5 hours ago
15 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का पूर्ण कर लिया हैं पार्ट 2 का कार्य प्रगति में है। -- as on 06-Jan-2024
Physical Peramenters