Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 0.300 | 0.85 | 0.000 | 0.000 |
68W204 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. of Uttarakhand E- letter No. 25463 PWD Anubhag-2, Dehradun 03-08-2022
TS Amount (lakhs) : 21.5 Lacs
Financial Detail
Sanction Cost : 31.51 Lacs
Resanction Cost : 31.51 Lacs
Exp. Upto Last Fy : 21.33 Lacs
For CFY 2024-2025
Remaining : 10.18 Lacs
Demand : 10.18 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 4.96 Lacs
Total Up to Date Exp : 26.29 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
1 year 9 months ago
03 Aug 2022
Tentative Completion date:
1 month 3 weeks from now
15 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का पूर्ण कर लिया हैं पार्ट 2 का कार्य प्रगति में है। -- as on 06-Jan-2024
Physical Peramenters