Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.4 | 3.4 | 0.000 | 3.4 | 3.400 | 0.000 |
68W226 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख सचिव उत्तराखण्ड शासन के ई0 पत्रावली सं0 -1/82314/2022, लो0नि0वि0 अनु0 -2 देहरादून दिनांक 15 दिसम्बर 2022
TS Amount (lakhs) : 240.43 Lacs
Financial Detail
Sanction Cost : 240.43 Lacs
Resanction Cost : 240.43 Lacs
Exp. Upto Last Fy : 3.55 Lacs
For CFY 2024-2025
Remaining : 236.88 Lacs
Demand : 180.00 Lacs
Allotment : 53.00 Lacs
Exp in CFY : 52.96 Lacs
Total Up to Date Exp : 56.51 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 30 %
Sanction on :
1 year 5 months ago
15 Dec 2022
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिग का कार्य पूर्ण एंव इण्टर कोट का कार्य प्रगति में है। -- as on 15-May-2024
Physical Peramenters