Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.4 | 3.4 | 0.000 | 3.4 | 3.400 | 0.000 |
68W226 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख सचिव उत्तराखण्ड शासन के ई0 पत्रावली सं0 -1/82314/2022, लो0नि0वि0 अनु0 -2 देहरादून दिनांक 15 दिसम्बर 2022
TS Amount (lakhs) : 240.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
240.43
Resanction Cost :
240.43
Tentative Cost :
240.43
Exp. Upto Last Fy : 3.55
For CFY 2024-2025
Remaining : 236.88
Demand : 225.00
Allotment : 103.01
Exp in CFY : 129.96
Total Up to Date Exp : 133.51
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 70 %
Sanction on :
1 year 7 months ago
15 Dec 2022
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग एवं इन्टर एवं टाॅप कोट का कार्य पूर्ण, पी0सी0 का कार्य प्रगति पर। -- as on 04-Jul-2024
Physical Peramenters