Work Profile

जनपद पौडी गढवाल के विकासखण्ड पोखडा में संगलाकोटी - भेडगांव - गुण्डिडा मोटर मार्ग के किमी0 5 से 9 में मरम्मत एवं पी0सी0 द्वारा नवीनीकरण का कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : C.E. PWD Uttarakhand Dehradun Letter No. 895/07 Yata-PMGSY- N III

TS Amount (lakhs) : 68.07 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

68.07

Resanction Cost :

68.07

Tentative Cost :

68.07

Exp. Upto Last Fy : 17.07

For CFY 2024-2025

Remaining : 51.00

Demand : 51.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 17.07

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
1 year 2 months ago
16 May 2023


Tentative Completion date:
4 weeks 18 hours from now
15 Aug 2024


Actual Completion Date:
Not Yet Reported


Rating : 116

Remark

Bottelneck: no issue


कार्य पूर्ण । -- as on 27-Mar-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4.8 4.8 4.8 0
Currently only Bank Gaurantee information is avilable