Work Profile Report [68W275]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : C.E PWD Uttarakhand Dehradun Letter No. 895/07 Yata-PMGSY-N III
TS Amount (lakhs) : 77.91 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.91
Resanction Cost :
77.91
Tentative Cost :
77.30
Saving
0.61
Exp. Upto Last Fy :
77.30
For CFY 2025-2026
Remaining :
0.61
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
77.30
Work completed
Sanction on : 2 years 1 month ago
16 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 11 months 1 week ago
30 Jul 2024
Actual Completion Date : 3 months 1 week ago
03 Apr 2025
Physical Linear Components
Remark
Overall Saving 0.61 has been recorded as expected cost of work reduced from 77.91 to 77.30 . -- as on 13-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand