Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21.07 | 21.07 | 21.07 | 0 |
68W275 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : C.E PWD Uttarakhand Dehradun Letter No. 895/07 Yata-PMGSY-N III
TS Amount (lakhs) : 77.91 Lacs
Financial Detail
Sanction Cost : 77.91 Lacs
Resanction Cost : 77.91 Lacs
Exp. Upto Last Fy : 47.84 Lacs
For CFY 2024-2025
Remaining : 30.07 Lacs
Demand : 30.07 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 47.84 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 week 3 days from now
30 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पैच मरम्मत का कार्य प्रगति पर है। -- as on 27-Mar-2024
Physical Peramenters