Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
68W289 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 49552 दिनांक 19/07/2023
TS Amount (lakhs) : 186.08 Lacs
Financial Detail
Sanction Cost : 186.08 Lacs
Resanction Cost : 186.08 Lacs
Exp. Upto Last Fy : 38.64 Lacs
For CFY 2024-2025
Remaining : 147.44 Lacs
Demand : 60.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 38.64 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 22 %
Up to Date : 25 %
Sanction on :
10 months 1 hour ago
19 Jul 2023
Tentative Completion date:
2 weeks 4 days ago
01 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिग का कार्य पूर्ण एंव इण्टर कोट का कार्य प्रगति में है। -- as on 15-May-2024
Physical Peramenters