Work Profile Report [68W290]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली सं0-49552 दिनांक 19/07/2023
TS Amount (lakhs) : 178.36 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
178.36
Resanction Cost :
178.36
Tentative Cost :
178.36
Exp. Upto Last Fy :
61.51
For CFY 2024-2025
Remaining :
116.85
Demand :
60.00
Allotment :
25.00
Exp in CFY :
0.00
Total Up to Date Exp :
61.51
Construction Started
Sanction on : 1 year 4 months ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
75 %
Tentative Completion date on : 5 months 1 week from now
04 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इन्टर कोट का कार्य पूर्ण एवं टॉप कोट का कार्य प्रगति पर है। -- as on 06-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand