Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
68W290 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली सं0-49552 दिनांक 19/07/2023
TS Amount (lakhs) : 178.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
178.36
Resanction Cost :
178.36
Tentative Cost :
178.36
Exp. Upto Last Fy : 61.51
For CFY 2024-2025
Remaining : 116.85
Demand : 60.00
Allotment : 15.00
Exp in CFY : 0.00
Total Up to Date Exp : 61.51
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 35 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
9 months 2 weeks from now
04 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिग का कार्य पूर्ण ।इण्टर कोट का कार्य प्रगति में हैं -- as on 25-Jun-2024
Physical Peramenters