Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.315 | 1.315 | 1.315 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
68W292 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0-पत्रावली सं0 48456 दिनांक 14/07/2023
TS Amount (lakhs) : 22.41 Lacs
Financial Detail
Sanction Cost : 22.41 Lacs
Resanction Cost : 22.41 Lacs
Exp. Upto Last Fy : 11.21 Lacs
For CFY 2024-2025
Remaining : 11.20 Lacs
Demand : 11.20 Lacs
Allotment : 11.17 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 11.21 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
1 month 1 week from now
01 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य प्रगति पर है। -- as on 27-Mar-2024
Physical Peramenters