Work Profile Report [68W294]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली सं0 48456 दिनांक 14/07/2023
TS Amount (lakhs) : 84.75 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.75
Resanction Cost :
84.75
Tentative Cost :
80.45
Saving
4.30
Exp. Upto Last Fy :
42.69
For CFY 2024-2025
Remaining :
42.06
Demand :
42.06
Allotment :
30.00
Exp in CFY :
29.76
Total Up to Date Exp :
72.45
Work completed
Sanction on : 1 year 5 months ago
14 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
10 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 4.3 has been recorded as expected cost of work reduced from 84.75 to 80.45 . -- as on 13-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: