Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.5 | 0 |
68W296 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रांक 26505 दिनाँक 08-09-2022
TS Amount (lakhs) : 109.57 Lacs
Financial Detail
Sanction Cost : 109.57 Lacs
Resanction Cost : 109.57 Lacs
Exp. Upto Last Fy : 18.76 Lacs
For CFY 2024-2025
Remaining : 90.81 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 18.76 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 8 months ago
08 Sep 2022
Tentative Completion date:
3 weeks 5 days from now
15 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिग का कार्य प्रगति में है। -- as on 20-Jan-2024
Physical Peramenters