Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13.52 | 13.52 | 13.52 | 0 |
68W317 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 48456 लोक निर्माण अनुभाग-2 दिनांक 23 फरवरी 2024
TS Amount (lakhs) : 215.04 Lacs
Financial Detail
Sanction Cost : 215.04 Lacs
Resanction Cost : 215.04 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 215.04 Lacs
Demand : 215.04 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
2 months 3 weeks ago
23 Feb 2024
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित कर लिया गया है, कार्य प्रगति पर है। -- as on 27-Mar-2024
Physical Peramenters