Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.25 | 7.25 | 0.000 | 7.25 | 0.000 | 0.000 |
68W319 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक 256/।।।(3)/2024-01(सी0आर0आई0एफ0)2022 लोक निर्माण अनुभाग-3 दिनांक 29 फरवरी 2024 एवं 294/।।।(3)/2024-01(सी0आर0आई0एफ0)2024 लोक निर्माण अनुभाग-3 दिनांक 12 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
701.80
Resanction Cost :
701.80
Tentative Cost :
701.80
Exp. Upto Last Fy : 25.00
For CFY 2024-2025
Remaining : 676.80
Demand : 250.00
Allotment : 70.00
Exp in CFY : 35.22
Total Up to Date Exp : 60.22
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 11 %
Sanction on :
4 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
10 months 3 weeks from now
11 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वर्तमान में मार्ग पर स्कपर निर्माण एवं सोलिग कलैक्शन का कार्य कार्य प्रगति पर है। -- as on 01-Jul-2024
Physical Peramenters