Work Profile Report [68W5]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी महोदय पत्र सं0 467/वा0fज0यो0 /2019-20/fदनांक 17.08.2020
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.29
Resanction Cost :
62.50
Tentative Cost :
62.50
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
62.50
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Unstarted Work
Sanction on : 5 years 1 week ago
17 Aug 2020
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 7 months 2 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 27-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand