Work Profile Report [69W125]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 4073 (1)/111 (2)/13-08 (प्रा0आ0)/2013 दि0 26.06.2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.71
Resanction Cost :
48.71
Tentative Cost :
48.71
Exp. Upto Last Fy :
6.60
For CFY 2024-2025
Remaining :
42.11
Demand :
46.26
Allotment :
42.11
Exp in CFY :
42.03
Total Up to Date Exp :
48.62
Work completed
Sanction on : 11 years 5 months ago
26 Jun 2013
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
30 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand