Work Profile Report [69W227]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5012/111 (2)/18-18 (एूूम0एल0ए0)/2017 दि0 05.10.2018
TS Amount (lakhs) : 94.02 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.02
Resanction Cost :
94.02
Tentative Cost :
70.90
Saving
23.12
Exp. Upto Last Fy :
94.02
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
94.02
Work completed
Sanction on : 6 years 9 months ago
05 Oct 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 1 week ago
30 Nov 2024
Actual Completion Date : 7 months 1 week ago
30 Nov 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 04-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: