Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21 | 21 | 0.000 | 21 | 0.000 | 0.000 |
No of Bridges | 3 | 3 | 0 | 3 | 0 | 0 |
Span of Bridges [m] | 362 | 362 | 0.000 | 362 | 0.000 | 0.000 |
69W289 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ाा0सं0 2531/111 -2/06-80 (प्रा0आ0)/05 दिनांक 30.08.06
TS Amount (lakhs) : 1433.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1579.80
Resanction Cost :
1579.80
Tentative Cost :
1579.80
Exp. Upto Last Fy : 1,186.09
For CFY 2024-2025
Remaining : 393.71
Demand : 25.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 1,186.09
none
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
17 years 10 months ago
30 Aug 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग के 21.00 कि0मी0 लम्बाई में मार्ग निर्माण कार्य पूर्ण। सेतु कार्य अवशेष। सेतु का स्थल चयन दि0 17.4.23 को कर लिया गया है। पूर्व निर्मित झूला पुल (सिंगटाली झूला पुल) के स्थान पर स्थल चयन कर लिया गया है। डिजायन कार्य हेतु कार्यवाही गतिमान है। -- as on 20-May-2023
Physical Peramenters