Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 0.000 | 0.000 |
69W301 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ाा0सं0 5316/111(2)/21-38 (एम0एल0ए0)2017 टी0सी0-2 दिनांक 02.11.2021
TS Amount (lakhs) : 103.69 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.69
Resanction Cost :
41.69
Tentative Cost :
41.69
Exp. Upto Last Fy : 33.57
For CFY 2024-2025
Remaining : 8.12
Demand : 8.12
Allotment : 8.12
Exp in CFY : 8.09
Total Up to Date Exp : 41.66
none
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
02 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 14-Dec-2023
Physical Peramenters