Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
69W316 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 428/111 (2)/16-14 (मु0म0घो0)/2015 दि0 23.01.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
69.15
Resanction Cost :
69.15
Tentative Cost :
69.15
Exp. Upto Last Fy : 62.80
For CFY 2024-2025
Remaining : 6.35
Demand : 6.35
Allotment : 6.34
Exp in CFY : 0.00
Total Up to Date Exp : 62.80
none
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
8 years 5 months ago
23 Jan 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भाग-1 व भाग-2 का कार्य पूर्ण। अधिकतम मुआवजा वितरण किया जा चुका है। अवशेष मुआवजा वितरण की कार्यवाही गतिमान है। -- as on 04-Nov-2023
Physical Peramenters