Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.8 | 15.8 | 16.800 | -1 | 0.000 | 0.000 |
69W319 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ाा0सं0 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 111 दि0 16.05.2023
TS Amount (lakhs) : 141.9 Lacs
Financial Detail
Sanction Cost : 141.90 Lacs
Resanction Cost : 141.90 Lacs
Exp. Upto Last Fy : 61.41 Lacs
For CFY 2024-2025
Remaining : 80.49 Lacs
Demand : 80.49 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 61.41 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर । -- as on 04-Sep-2023
Physical Peramenters