Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.35 | 1.35 | 0.000 | 1.35 | 0.000 | 0.000 |
69W335 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 36087 लोक निर्माण अनुभाग-2 दि0 30.06.2023
TS Amount (lakhs) : 79.78 Lacs
Financial Detail
Sanction Cost : 79.78 Lacs
Resanction Cost : 79.78 Lacs
Exp. Upto Last Fy : 31.99 Lacs
For CFY 2024-2025
Remaining : 47.79 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.99 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 months 2 weeks ago
30 Jun 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 05-Oct-2023
Physical Peramenters