Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.82 | 0.82 | 0.000 | 0.82 | 0.000 | 0.000 |
69W337 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 36087 लोक निर्माण अनुभाग-2 दि0 30.06.2023
TS Amount (lakhs) : 53.01 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
53.01
Resanction Cost :
53.01
Tentative Cost :
53.01
Exp. Upto Last Fy : 6.05
For CFY 2024-2025
Remaining : 46.96
Demand : 40.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
G1 का कार्य पूर्ण,
G2 का कार्य प्रगति पर।
-- as on 25-Jun-2024
Physical Peramenters