Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 60.44 | 60.44 | 0.000 | 60.44 | 0.000 | 0.000 |
69W339 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2491/111 (2)/23-01 (प्रा0आ0)/2023 दि0 21.07.2023
TS Amount (lakhs) : 971.24 Lacs
Financial Detail
Sanction Cost : 971.24 Lacs
Resanction Cost : 971.24 Lacs
Exp. Upto Last Fy : 636.86 Lacs
For CFY 2024-2025
Remaining : 334.38 Lacs
Demand : 334.38 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 636.86 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 08-Apr-2024
Physical Peramenters