Work Profile Report [69W360]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0 देहरादून का पत्रांक 1588/01 नियो0-2(एस0डी0आर0एफ0)/2023 दिनांक 30.12.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.67
Resanction Cost :
46.67
Tentative Cost :
46.67
Exp. Upto Last Fy :
28.90
For CFY 2024-2025
Remaining :
17.77
Demand :
17.77
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
28.90
Work completed
Sanction on : 10 months 3 weeks ago
30 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand