Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.775 | 5.775 | 5.775 | 0 |
69W365 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 48456 दिनांक 30 जनवरी 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
130.63
Resanction Cost :
130.63
Tentative Cost :
130.63
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 130.63
Demand : 130.63
Allotment : 130.63
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
4 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5 किमी लम्बाई में PC का कार्य पूर्ण,
शेष कार्य प्रगति पर।
-- as on 01-Jul-2024