Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22 | 22 | 22 | 0 |
69W367 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 272/111 (2)/2024-01(प्रा0आ0)/2023 दिनांक 31 जनवरी 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
517.65
Resanction Cost :
517.65
Tentative Cost :
517.65
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 517.65
Demand : 517.65
Allotment : 231.67
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर । -- as on 29-Jun-2024