Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
69W94 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 7235/111 (2)/11-139 (प्रा0आ0)/2011 दि0 24.12.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.20
Resanction Cost :
88.20
Tentative Cost :
88.20
Exp. Upto Last Fy : 58.10
For CFY 2024-2025
Remaining : 30.10
Demand : 30.10
Allotment : 2.00
Exp in CFY : 0.10
Total Up to Date Exp : 58.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
12 years 6 months ago
24 Dec 2011
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
सैद्धान्तिक स्वीकृति में अधिरोपित शर्तो का अनुपालन करते हुए विधिवत स्वीकृति हेतु आख्या दिनांक 26.01.2021 को ऑन लाईन अपलोड कर दी गयी है। मार्ग निर्माण का कार्य पूर्ण किया जा चुका है। -- as on 03-Jan-2024
Physical Peramenters