Work Profile Report [6W119]

बागेश्वर में रमाणी कनौली मोटर मार्ग का किचवा तक विस्तार कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008

TS Amount (lakhs) : 147 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

147.00

Resanction Cost :

147.00

Tentative Cost :

140.00

Saving

7.00

Exp. Upto Last Fy :

131.58

For CFY 2025-2026

Remaining :

15.42

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

131.58

Work completed

Sanction on : 17 years 5 months ago

25 Jul 2008

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 years 10 months ago

24 Feb 2021

Actual Completion Date : 5 years 9 months ago

01 Apr 2020

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4
4.000
0
0.000
0.000

Remark

view all

Overall Saving 7 has been recorded as expected cost of work reduced from 147 to 140 . -- as on 10-Dec-2025

Rating : 100

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: