Work Profile Report [6W123]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 287.7 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
287.70
Resanction Cost :
287.70
Tentative Cost :
287.70
Exp. Upto Last Fy :
139.64
For CFY 2024-2025
Remaining :
148.06
Demand :
51.00
Allotment :
0.00
Exp in CFY :
36.16
Total Up to Date Exp :
175.80
Construction Started
Sanction on : 16 years 4 months ago
25 Jul 2008
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
55 %
Tentative Completion date on : 7 months 2 weeks from now
10 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3 किमी कार्य पूर्ण।
किमी0 2 में 18 मी0 सेतु निर्माण कार्य प्रगति पर।
-- as on 20-Nov-2024
Assets :
© PWD Uttarakhand