Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 3.000 | 3 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 0 | 2 | 1 | 0 |
6W123 :
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 287.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
287.70
Resanction Cost :
287.70
Tentative Cost :
287.70
Exp. Upto Last Fy : 139.64
For CFY 2024-2025
Remaining : 148.06
Demand : 85.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 139.64
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
1 year 5 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
3 किमी कार्य पूर्ण।
किमी0 1 में 18 मी0 सेतु निर्माण हेतु अनुबंध गठन की कार्यवाही की जा रही है। सेतु का कार्य पूर्ण होने के उपरान्त अवशेष 3 किमी0, 1 सेतु हेतु पुनरीक्षित आगणन गठित कर प्रेषित किया जाएगा।
-- as on 06-Apr-2024
Physical Peramenters