Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
6W126 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 133.61 Lacs
Financial Detail
Sanction Cost : 211.68 Lacs
Resanction Cost : 211.68 Lacs
Exp. Upto Last Fy : 128.18 Lacs
For CFY 2024-2025
Remaining : 83.50 Lacs
Demand : 70.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 128.18 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
15 years 9 months ago
25 Jul 2008
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
15 मी0 सेतु के अबटमेंट निर्माण का कार्य प्रगति पर। -- as on 06-Apr-2024
Physical Peramenters