Work Profile Report [6W126]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 133.61 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
211.68
Resanction Cost :
211.68
Tentative Cost :
211.68
Exp. Upto Last Fy :
128.18
For CFY 2024-2025
Remaining :
83.50
Demand :
60.00
Allotment :
0.00
Exp in CFY :
2.54
Total Up to Date Exp :
130.72
Construction Started
Sanction on : 16 years 3 months ago
25 Jul 2008
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
65 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
15 मी0 सेतु के अबटमेंट निर्माण का कार्य प्रगति पर। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand