Work Profile

बागेश्वर में भलोढी मोटर मार्ग सेतु सहित


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008

TS Amount (lakhs) : 133.61 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

211.68

Resanction Cost :

211.68

Tentative Cost :

211.68

Exp. Upto Last Fy : 128.18

For CFY 2024-2025

Remaining : 83.50

Demand : 70.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 128.18

Construction Started

Physical Progress:

At start of FY 2024-2025 : 65 %

Up to Date : 65 %

Sanction on :
15 years 11 months ago
25 Jul 2008


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 77

Remark

Forest Status 21: Final

Bottelneck: no issue


15 मी0 सेतु के अबटमेंट निर्माण का कार्य प्रगति पर। -- as on 06-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 3 3 3.000 0 0.000 0.000
No of Bridges 1 1 0 1 1 0
Currently only Bank Gaurantee information is avilable