Work Profile Report [6W166]
Fin Plan
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी बागेश्वर के पत्रांक सं0 929/fज0यो0 /2010-11 fद0 17 अगस्त, 2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy :
4.99
For CFY 2024-2025
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.99
Work completed
Sanction on : 2 years 8 months ago
31 Mar 2022
Physical Progress:
At start of FY 2024-2025 :
98 %
Up to Date :
0 %
Tentative Completion date on : 10 years 8 months ago
31 Mar 2014
Actual Completion Date : 10 years 9 months ago
01 Mar 2014
Physical Linear Components
Remark
कार्य पूर्ण । दायित्व शेष। वेद प्रकाश कनि0अभि0)
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: 60 Meter Span steel girder Motor bridge