Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
6W294 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2198/(1)/111(2)/13-61(प्रा0आ0)/2012 दिनांक 28 मार्च, 2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 7.39
For CFY 2024-2025
Remaining : 30.41
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.28
Total Up to Date Exp : 7.67
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
11 years 3 months ago
28 Mar 2013
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
1 month 1 week ago
04 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 04-Jun-2024