Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
6W501 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 3057/।।।(2)/16-46 (एम0एल0ए0)/2015 दिनांक 29 नवम्बर, 2016
TS Amount (lakhs) : 6.63 Lacs
Financial Detail
Sanction Cost : 79.90 Lacs
Resanction Cost : 79.90 Lacs
Exp. Upto Last Fy : 6.75 Lacs
For CFY 2024-2025
Remaining : 73.15 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.75 Lacs
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
7 years 5 months ago
29 Nov 2016
Tentative Completion date:
1 year 7 months from now
30 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
मुआवजा वितरित किया जाना है। 5 किमी0 पहाड़ कटान हेतु आगणन प्रेषित। -- as on 28-Apr-2024
Physical Peramenters