Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 2.750 | 0.000 |
6W567 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0ं 595/।।।(2)/19-46 (एम0एल0ए0)/2017 टी0सी0-ं। दिनांक 07.02.2019
TS Amount (lakhs) : 328.21 Lacs
Financial Detail
Sanction Cost : 328.21 Lacs
Resanction Cost : 328.21 Lacs
Exp. Upto Last Fy : 80.54 Lacs
For CFY 2024-2025
Remaining : 247.67 Lacs
Demand : 100.00 Lacs
Allotment : 120.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 80.54 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
5 years 3 months ago
07 Feb 2019
Tentative Completion date:
1 year 3 months from now
31 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.75 किमी0 पहाड कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 30-Mar-2024
Physical Peramenters