Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 2.750 | 0.000 |
6W567 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0ं 595/।।।(2)/19-46 (एम0एल0ए0)/2017 टी0सी0-ं। दिनांक 07.02.2019
TS Amount (lakhs) : 328.21 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
328.21
Resanction Cost :
328.21
Tentative Cost :
328.21
Exp. Upto Last Fy : 80.54
For CFY 2024-2025
Remaining : 247.67
Demand : 100.00
Allotment : 61.81
Exp in CFY : 0.00
Total Up to Date Exp : 80.54
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
5 years 5 months ago
07 Feb 2019
Tentative Completion date:
4 months 3 weeks from now
14 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.75 किमी0 पहाड कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 30-Mar-2024
Physical Peramenters