Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 1.57 | 1.570 | 0 | 0.000 | 0.000 |
6W570 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0ं 596/।।।(2)/19-46 (एम0एल0ए0)/2017 टी0सी0-ं। दिनांक 07.02.2019
TS Amount (lakhs) : 123.01 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
123.01
Resanction Cost :
123.01
Tentative Cost :
123.01
Exp. Upto Last Fy : 95.92
For CFY 2024-2025
Remaining : 27.09
Demand : 22.00
Allotment : 3.77
Exp in CFY : 3.97
Total Up to Date Exp : 99.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
07 Feb 2019
Tentative Completion date:
1 year 3 months ago
19 Mar 2023
Actual Completion Date:
3 years 3 months ago
01 Apr 2021
Remark
Bottelneck: no issue
कार्य पूर्ण।
दलदले भाग में इंटर लोकिंग टाइल्स लगाने का कार्य प्रगति पर।
-- as on 12-Apr-2024
Physical Peramenters