Work Profile Report [6W572]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1179/।।।(2)/19-46(एम0एल0ए0)/2017 टी0सी0-।ं दिनांक 27 फरवरी 2019
TS Amount (lakhs) : 242.8 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
242.80
Resanction Cost :
242.80
Tentative Cost :
178.00
Saving
64.80
Exp. Upto Last Fy :
167.68
For CFY 2025-2026
Remaining :
75.12
Demand :
8.00
Allotment :
8.25
Exp in CFY :
7.72
Total Up to Date Exp :
175.40
Work completed
Sanction on : 6 years 9 months ago
27 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 11 months ago
07 Jan 2023
Actual Completion Date : 2 years 11 months ago
07 Jan 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: