Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
6W573 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: 10 meter R.C.C. Motor Bridge
Administrative Approval Detail : शा0सं0 1179/।।।(2)/19-46(एम0एल0ए0)/2017 टी0सी0-।ं दिनांक 27 फरवरी 2019
TS Amount (lakhs) : 176.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
176.26
Resanction Cost :
176.26
Tentative Cost :
176.26
Exp. Upto Last Fy : 158.36
For CFY 2024-2025
Remaining : 17.90
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 158.36
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
27 Feb 2019
Tentative Completion date:
2 years 5 months ago
31 Jan 2022
Actual Completion Date:
2 years 5 months ago
30 Jan 2022
Remark
Bottelneck: no issue
कार्य पूर्ण । पी0सी0आर0 मुख्य अभियंता के पत्र सं0 4331/336याता0-कु0/2022 दिनांक 21.09.2022 द्वारा प्रमुख अभियंता एवं विभागाध्यक्ष देहरादून को प्रेषित। -- as on 06-Oct-2023
Physical Peramenters