Administrative Approval Detail : शासनादेश सं0 1831/।।।(2)/20-46 (एम0एल0ए0) /2017 दिनांक 06 अक्टूबर, 2020
TS Amount (lakhs) : 68.7 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
68.70
Resanction Cost :
68.70
Tentative Cost :
68.70
Exp. Upto Last Fy :
0.57
For CFY 2025-2026
Remaining :
68.13
Demand :
65.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.57
Construction Started
Sanction on : 4 years 8 months ago
06 Oct 2020
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
20 %
Tentative Completion date on : 6 months 3 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति पर है। -- as on 18-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: