Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 12 | 12 | 0.000 | 12 | 0.000 | 0.000 |
6W597 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 233(ं।)/।।।(2)/21 -46(एम0एल0ए0)/2017 टी0सी0आई0 दिनांक 15.02.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 28.88 Lacs
Resanction Cost : 28.88 Lacs
Exp. Upto Last Fy : 2.71 Lacs
For CFY 2024-2025
Remaining : 26.17 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.71 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
3 years 3 months ago
15 Feb 2021
Tentative Completion date:
2 years 7 months from now
31 Dec 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
समरेखण प्रस्ताव गठित किया जा रहा है। -- as on 05-Mar-2024
Physical Peramenters