Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
6W601 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1388/।।।(2)/21-46(एम0एल0ए0)/2017 पी0सी0 दिनांक 21.05.2021
TS Amount (lakhs) : 5.8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
46.48
Resanction Cost :
46.48
Tentative Cost :
46.48
Exp. Upto Last Fy : 7.30
For CFY 2024-2025
Remaining : 39.18
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.30
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
3 years 1 month ago
21 May 2021
Tentative Completion date:
1 year 1 month from now
30 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
सैद्धान्तिक स्वीकृति प्राप्त। द्वितीय चरण की स्वीकृति हेतु आगणन प्रेषित। -- as on 05-Jul-2021
Physical Peramenters