Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
6W601 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1388/।।।(2)/21-46(एम0एल0ए0)/2017 पी0सी0 दिनांक 21.05.2021
TS Amount (lakhs) : 5.8 Lacs
Financial Detail
Sanction Cost : 46.48 Lacs
Resanction Cost : 46.48 Lacs
Exp. Upto Last Fy : 7.30 Lacs
For CFY 2024-2025
Remaining : 39.18 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.30 Lacs
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
2 years 11 months ago
21 May 2021
Tentative Completion date:
1 year 3 months from now
30 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
सैद्धान्तिक स्वीकृति प्राप्त। द्वितीय चरण की स्वीकृति हेतु आगणन प्रेषित। -- as on 05-Jul-2021
Physical Peramenters