Work Profile Report [6W657]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : dsto letter no 525/जि0यो0(1)/2021-22, dated 05-07-2021
TS Amount (lakhs) : 50 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.00
Resanction Cost :
30.00
Tentative Cost :
30.00
Exp. Upto Last Fy :
11.51
For CFY 2024-2025
Remaining :
18.49
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11.51
Construction Started
Sanction on : 3 years 4 months ago
05 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
60 %
Tentative Completion date on : 1 month 6 days from now
30 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 14-Dec-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand