Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 72 | 72 | 0.000 | 72 | 0.000 | 0.000 |
6W679 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2615/।।।(2)/21-46(एम0एल0ए0)/2017 दिनांक 10.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.44
Resanction Cost :
64.44
Tentative Cost :
64.44
Exp. Upto Last Fy : 1.05
For CFY 2024-2025
Remaining : 63.39
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.05
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
2 years 11 months ago
10 Aug 2021
Tentative Completion date:
1 year 3 months from now
31 Oct 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
समरेखण प्रस्ताव अधी0 अभियंता के पत्र सं0 5805/463सी0-01/2022-23 दिनांक 16.12.2022 द्वारा 6 किमी0 लंबाई हेतु अनुमोदित। पिलरोें का निर्माण कर लिया गया है। पेडों की गणना कर सूची प्राप्त। वनभूमि गठन की कार्यवाही प्रगति पर। -- as on 07-Dec-2023
Physical Peramenters