Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
6W684 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 4799(1)/।।।(2)/21- 46(एम.एल.ए.)/2017 दिनांक 06.10.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
15.00
Resanction Cost :
15.00
Tentative Cost :
15.00
Exp. Upto Last Fy : 0.01
For CFY 2024-2025
Remaining : 14.99
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.01
Survey work done
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
2 years 9 months ago
06 Oct 2021
Tentative Completion date:
1 year 8 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
गा्रमीणों द्वारा खडिया की माइन्स आने के कारण समरेखण में विवाद है। विवाद सुलझाने हेतु प्रयास किया जा रहा है। -- as on 28-Apr-2024
Physical Peramenters