Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
6W689 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ‘शा.सं. 5300/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0प्ट दिनांक 01.11.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 20.70 Lacs
Resanction Cost : 20.70 Lacs
Exp. Upto Last Fy : 1.77 Lacs
For CFY 2024-2025
Remaining : 18.93 Lacs
Demand : 0.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.77 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
2 years 6 months ago
01 Nov 2021
Tentative Completion date:
1 year 7 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
समरेखण प्रस्ताव अनुमोदित। वनभूमि प्रस्ताव गठित। -- as on 28-Apr-2024
Physical Peramenters