Work Profile Report [6W703]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ‘शा.सं. 5663/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0 दिनांक 17.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.07
Resanction Cost :
53.07
Tentative Cost :
53.07
Exp. Upto Last Fy :
0.23
For CFY 2024-2025
Remaining :
52.84
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.23
Alignment Approved
Sanction on : 3 years 1 month ago
17 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
26 %
Tentative Completion date on : 10 months 6 days from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण प्रस्ताव पत्र सं0 3098/181सी0-01/2024-25 दिनांक 09.07.2024 द्वारा लंबाई 3.75 किमी0+4 no Bridge हेतु अनुमोदित। -- as on 22-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: