Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.6 | 2.6 | 0.860 | 1.74 | 1.740 | 1.740 |
6W718 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ‘शा.सं. पी0डब्ल्यू0डी02-बी0यू0डी0/ए0एन0बी0यू0/4/2022-।।।-2-पब्लिक वक्र्स डिपार्टमेंट (कम्प्यूटर न0 31978 दिनांक 26.08.2022
TS Amount (lakhs) : 180.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
180.25
Resanction Cost :
180.25
Tentative Cost :
180.25
Exp. Upto Last Fy : 114.37
For CFY 2024-2025
Remaining : 65.88
Demand : 54.00
Allotment : 49.57
Exp in CFY : 49.57
Total Up to Date Exp : 163.95
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 100 %
Sanction on :
1 year 10 months ago
26 Aug 2022
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
1 month 2 weeks ago
01 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 01-Jun-2024
Physical Peramenters