Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
No of Bridges | 5 | 5 | 0 | 5 | 0 | 0 |
6W719 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ‘शा0सं0 63178 दिनांक 15.09.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.32
Resanction Cost :
40.32
Tentative Cost :
40.32
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 40.22
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Survey work done
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
1 year 10 months ago
15 Sep 2022
Tentative Completion date:
1 year 1 week from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव गठित कर लिया गया है। -- as on 28-Feb-2024
Physical Peramenters