Work Profile Report [6W719]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ‘शा0सं0 63178 दिनांक 15.09.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.32
Resanction Cost :
40.32
Tentative Cost :
40.32
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
40.22
Demand :
1.20
Allotment :
1.19
Exp in CFY :
1.19
Total Up to Date Exp :
1.29
Alignment Approved
Sanction on : 3 years 3 months ago
15 Sep 2022
Physical Progress:
At start of FY 2025-2026 :
26 %
Up to Date :
26 %
Tentative Completion date on : 7 months 2 weeks from now
31 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों संग विवाद नहीं सुलझ सका है। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: