Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 1.8 | 0.000 | 1.8 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
6W721 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाइल सं0 23938 दिनांक 27.07.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.60
Resanction Cost :
18.60
Tentative Cost :
18.60
Exp. Upto Last Fy : 8.44
For CFY 2024-2025
Remaining : 10.16
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 8.44
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
1 year 11 months ago
27 Jul 2022
Tentative Completion date:
1 year 3 months from now
31 Oct 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा वितरण की कार्यवाही की जा रही है। -- as on 16-Apr-2023
Physical Peramenters