Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
6W726 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला0 बागे0 के पत्र सं0 70/तेरह-16सी0आर0ए0/अनटाईड फण्ड 2021-22 दिनांक 17.11.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 4.99 Lacs
Resanction Cost : 4.99 Lacs
Exp. Upto Last Fy : 2.94 Lacs
For CFY 2024-2025
Remaining : 2.05 Lacs
Demand : 1.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.94 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
1 year 6 months ago
17 Nov 2022
Tentative Completion date:
6 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Feb-2023
Physical Peramenters