Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.85 | 6.85 | 5.500 | 1.35 | 0.000 | 0.000 |
6W734 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 41349 दिनांक 20.12.2022
TS Amount (lakhs) : 131.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
341.25
Resanction Cost :
131.19
Tentative Cost :
131.19
Exp. Upto Last Fy : 54.58
For CFY 2024-2025
Remaining : 76.61
Demand : 80.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 54.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 6 months ago
20 Dec 2022
Tentative Completion date:
2 days 18 hours from now
20 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.50 किमी0 पहाड कटान पूर्ण। अवशेष कार्य प्रगति पर। -- as on 30-Mar-2024
Physical Peramenters