Work Profile Report [6W734]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइत संख्या 41349 दिनांक 20.12.2022
TS Amount (lakhs) : 131.19 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
341.25
Resanction Cost :
131.19
Tentative Cost :
80.00
Saving
51.19
Exp. Upto Last Fy :
54.58
For CFY 2024-2025
Remaining :
76.61
Demand :
23.00
Allotment :
2.67
Exp in CFY :
2.67
Total Up to Date Exp :
57.25
Work deferred
Sanction on : 2 years 4 days ago
20 Dec 2022
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
70 %
Tentative Completion date on : 5 days 28 minutes from now
30 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 51.19 has been recorded as expected cost of work reduced from 131.19 to 80 . -- as on 18-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: