Work Profile Report [6W740]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइत संख्या 50154 दिनांक 28.03.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy :
2.27
For CFY 2025-2026
Remaining :
2.23
Demand :
0.40
Allotment :
0.39
Exp in CFY :
0.39
Total Up to Date Exp :
2.66
Alignment Approved
Sanction on : 2 years 8 months ago
28 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
26 %
Up to Date :
26 %
Tentative Completion date on : 1 year 2 weeks from now
31 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वृक्षों के गणना की सूची अभी भी अप्राप्त है। -- as on 29-Nov-2025
Assets :
Work not linked with IM